P. Manual for the preparation of estimates (estimates) for commissioning work on electrical devices - Shipulina N.P. Scheme for the formation of a signaling section

Shipulina N.P. Manual for the preparation of estimates (estimates) for commissioning work on electrical devices - Moscow, 2005. - 188 p.
Download(direct link) : posobieposostavleniusmetnih2005.djvu Previous 1 .. 58 > .. >> Next
technological parameters and mutual control of operating modes.
Technological complex, including units in the amount of up to 10
pcs."1set*
01-13-030-0G1 "Centralized (dispatch) control systems
areas included in the common technological complex. Technological
a complex that includes managed plots in the amount of up to 5
pcs.set*
11.1.9. Estimate No. 9. Initial data
Yu """ BUS SYSTEM 10KV" "9" COMMISSIONING OF ELECTRICAL EQUIPMENT AND
FOR RZA DEVICES "FEDERAL UNIT PRICES FOR COMMISSIONING
FERp-2001. COLLECTION N1. ELECTRICAL DEVICES. TYPICAL DIAGRAM (OR
CODE OF A SPECIFIC SCHEME)" *
148


Note line (P) indicates:
P ADJUSTMENT WORKS. THE ESTIMATE INCLUDES OVERHEAD COST RATES 65% (MDS 81
-33.2004.APP.4.P48), ESTIMATED PROFIT 60% (MDS-25.2001
.APP.3,P48).OP.2.1 .T1 .P5. PERFORMANCE OF COMMISSIONING WORKS IN
ELECTRICAL INSTALLATIONS THAT ARE UNDER VOLTAGE WITH DESIGN
OF THE PERMIT OR INSTRUCTION COEFFICIENT 1.3 FOR 85% OF THE COST К= 1.255
(K \u003d 1 + 0.3.0.85 \u003d 1.255).
INSTALLATION WORKS CARRIED OUT WITH ATTRACTION OF FUNDS OF THE FEDERAL BUDGET,
IN THE CITY OF MOSCOW TO THE PRICES OF FER-2001. INTRODUCED BY A LETTER OF THE RF GOSSTROY
FOR DECEMBER 2004 (K=4.98)*
01-03-002-04 "2" Three-pole switch with voltage up to 1 kV
electromagnetic, thermal or combined release, rated
current up to 50 A "pcs. *
01-04-034-02"1 "Complete devices protection and automation series SPAC-
800"set*
01 -04-063-0 And "Arc protection of sections of complete distribution
devices (KRU) "set *
01-05-023-02 "1" ACR device with subsequent automatic reclosure after restoration
frequency"device*
01-06-020-03 "2" Secondary circuits of the voltage transformer three-
phase "system *
01 -06-021-01"2"Wiring diagram of a three-wire system with the number
panels (cabinets, cells) up to 2 "scheme *
01-06-021-02 "2" Wiring diagram of a three-wire system, for each

01-06-021-0Г5 "Wiring diagram of a three-wire system with the number of panels
(cabinets, cells) up to 2 "scheme *
01-06-021-02 "65" Wiring diagram of a three-wire system, for each
subsequent panel (cabinet, cell) over 2 "scheme *
01-06-022-01"5"Scheme of redundant power supply of a three-wire system from
other power supply with manual switch device"-diagram*
01 -06-023-01 "1 "Voltage level control device for AC or
rectified operational current "device *
01 -09-001-01 "3" Contact mechanical sensor with the number of control circuits
up to 2"*
01-09-010-03 "1" Relay contactor control functional group with
total number external interlocking connections up to Yu "pcs. *
149
A guide to the preparation of estimates (estimates)
on the commissioning works on electrical devices

Z "pcs. *
01-09-002-01 "3" Non-contact analog sensor with "input-output" number up to
Z "pcs. *
01-09-011-02 "2" Functional control group analog non-contact
with a total number of elements and settings up to 5 "pcs. *
01-10-001-01 "12" Collection and implementation of information signals of protection devices,

01-10-002-01 "4" Scheme of formation of the signaling section (central,
technological, local, emergency, preventive, etc.) "section *
01-10-003-01 "G" Mnemonic diagram of the dispatch control board with the number
received signals up to 50 "circuit *
01-10-010-01 "G" Scheme for monitoring the insulation of the electrical network using
electrical measuring instruments "diagram *
01-10-010-02"1 "Scheme for monitoring the insulation of an electrical network using
relay-contactor equipment and non-contact elements - diagram *
01-10-001-01 "15" Collection and implementation of information signals of protection devices,
automation of electrical and technological modes "signal *
01-10-001-01 "6" Collection and implementation of information signals of protection devices,
automation of electrical and technological modes "signal *
The following rates are applied with coefficient K=1.255, for payment and
labor costs:
01-02-016-02 "1" Three-phase voltage transformer with voltage up to 11
kV "pcs. *
01-11-010-03"1"Measurement of resistance to current spreading of the circuit with
diagonal, m, up to 200 "1meas. *
01-11-011-0G0.82 "Checking the presence of a circuit between grounding and grounded
elements"YPoint*
01-11-024-02 "6" Phasing electrical line or transformer with network
voltage, kV, St. 1"1phase*
01-11-026-02"12"Removal, processing and analysis of vector diagrams"1diagram*
01-11-028-01 "2" Measurement of insulation resistance with a megohmmeter of cable and
other lines with voltage up to 1 kV intended for transmission
electricity to switchgears, shields, cabinets,
switching devices and electrical consumers "1 line*
150
"Mo-" ¦ Off."
A guide to the preparation of estimates (estimates)

Introductory Instructions

1. This section contains prices for commissioning for independent schemes signaling (central, technological, local, emergency, warning, etc.) including light and sound signals, as well as circuits for monitoring the insulation of the electrical network.

2. The prices take into account the costs of the following commissioning works performed in accordance with the requirements of the "Electrical Installation Rules", as well as SNiP 3.05.06-85 "Electrical Devices":

check and adjustment of relays and equipment;

adjustment of flashing light devices;

testing devices and signaling schemes for operation.

3. The prices do not take into account and should be determined additionally according to the prices of other departments of the Collection, the costs of commissioning for:

switching devices and their secondary switching circuits - in department 03;

wiring diagrams for signaling circuits - in department 06;

sensors from which the signal enters the circuit automatic control- in department 09;

high voltage tests according to department 12.

Rate code

Labor costs, man-hour

Section 1. ALARM SCHEMES

Table Schemes for collecting and implementing information signals

Meter: signal

Collection and implementation of information signals of protection devices, automation of electrical and technological modes

Table Schemes for the formation of the signaling section

Meter: plot

The scheme of formation of the signaling section (central, technological, local, emergency, warning, etc.)

Table Mimic diagrams of the supervisory control panel

Meter: scheme (prices from 01 to 03); 100 signals (price 04)

Mnemonic diagram of the supervisory control panel with the number of received signals up to:

for every 100 subsequent signals add to the price 03

Section 2. ELECTRICAL NETWORK INSULATION CONTROL SCHEMES

Table Electric network insulation control scheme

Meter: circuit

Control circuit:

using electrical measuring instruments

with the use of relay-contactor equipment and non-contact elements

SECTION 11. MEASUREMENTS IN ELECTRICAL INSTALLATIONS


Introductory Instructions

1. This section contains prices for special tests and measurements in the course of work on electrical cables and in electrical installations.

2. The prices take into account the labor costs for the following commissioning works performed in accordance with the requirements of the "Electrical Installation Rules", as well as SNiP 3.05.06-85 "Electrical Devices":

choice of measurement method;

assembly and disassembly of test circuits;

ensuring special safety measures at the test (measurement) object;

measurement production.

3. Prices from 2 to 5, 1, 1 take into account the costs of installing auxiliary electrodes and their connection to measuring instruments and the measured object.

4. Rates table. applies only to electric cars and devices installed in power circuits.

5. For this section, prices for commissioning works are determined that are not taken into account by prices for other departments of the Collection.

6. Price 1 takes into account the costs of performing work for a three-wire line. For a two-wire or four-wire line, the price should be determined at a price of 1 with a coefficient of 0.7 and 1.3, respectively.

Rate code

Name and technical specifications equipment

Direct costs (compensation of commissioning personnel), rub.

Labor costs, man-hour

Section 1. CABLE WORK

Table Search and location of cable damage with burning

Meter:I cable (prices 01 and 02); 500 m cable (price 3)

Search and determination of the location of cable damage with burning, cable length, m, up to:

for each subsequent 500 m add to the price 02

Table Determination of active resistance or working electrical capacitance of a cable core

Meter: 1 measurement

Determination of active resistance or working electrical capacitance of a cable core for voltage, kV, up to:

Section 2. GROUNDING DEVICES

Table Measurement of resistance to current spreading

Meter: 1 measurement

Current flow resistance measurement:

ground electrode

contour with a diagonal, m, up to:

Table Checking the presence of a circuit between grounding conductors and grounded elements

Measuring points

Checking the presence of a circuit between grounding conductors and grounded elements

Table Definition resistivity soil

Meter: 1 measurement

Determination of soil resistivity

Table Measurement of the impedance of the phase-zero circuit

Meter: 1 pantograph

Measurement of the impedance of the "phase-zero" circuit

Table Characterization for determining the contact voltage

Meter: 1 touch point

Characterization for determining the touch voltage at the points specified in the project, in networks with a voltage of over. 1 kV

Measurement of touch voltage in 380/220 V networks with solidly grounded neutral

Section 3. OTHER MEASUREMENTS

Table Measurement of the dielectric loss tangent

Meter: 1 measurement

Measurement of the dielectric loss tangent

Table Dimension transitional resistances direct current

Meter: 1 measurement

Measurement of transient resistance to direct current of the contacts of the busbars of distribution devices with voltage, kV, up to:

Table Measurement of active, inductive resistances, capacitance of electrical machines and devices

Meter: 1 measurement

Measurement of active, inductive resistance and capacitance of electrical machines and devices

Table Characterization

Gauge: 1 characteristic

Removal of characteristics of switching devices:

temporary

high-speed

Table Phasing of an electric line or transformer

Meter: 1 phasing

Phasing of an electric line or transformer with a voltage network, kV:

Table Measurement of absorption coefficient and non-linearity of insulation

Meter: 1 measurement

Coefficient measurement:

winding absorption of transformers and electrical machines

non-linearity of electrical machine insulation

Table Acquisition of oscillograms and vector diagrams

Meter:I oscillogram (price 01); 1 diagram (price 02)

Removal, processing and analysis:

oscillograms

vector diagrams

Table Measurement of leakage currents or breakdown voltage

Table 1-143

Functional control groups analog?? contactless

Norms for 1 pc.

Table 1-144

Functional control groups discrete?? contactless

Norms for 1 pc.

Table 1-145

Circuits of automatic control systems

Norms for 1 pc.

SECTION 10. DEVICES AND SIGNALING CIRCUITS

Introductory Instructions

1. This section provides the labor costs for commissioning for independent signaling circuits (central, technological, local, emergency, warning, etc.), including light and sound signals, as well as electric network insulation monitoring circuits.

2. The rates, in addition to those listed in clause 6 of the technical part, take into account the costs of the following commissioning work performed in accordance with the requirements of the rules for electrical installations, as well as SNiP 3.05.06-85 "Electrical devices":

testing and adjustment of relay-contactor equipment;

setting the time relay settings;

adjustment of flashing light devices;

testing devices and signaling schemes for operation.

3. The norms do not take into account and should be determined additionally according to the norms of other departments of the collection, the costs of commissioning for:

switching devices and their secondary switching circuits - in department 3;

wiring diagrams for signaling circuits - for department 6;

sensors, from which the signal enters the automatic control circuit - according to department 9;

high voltage tests - according to department 12.

4. In the composition of works according to the table. 1-146 includes checking the signaling circuits from the first intermediate terminal block of the devices that form the signal to the signaling section by creating a mode or their artificial imitation (in the absence of a signal implementation section, it is carried out directly to a light or sound signal).

5. In the composition of works according to the table. 1-147 includes setting up the alarm section equipment and ensuring the operation of light, sound and other alarms (including the RIS relay).

6. The norms of this section are calculated based on the conditions for the implementation of commissioning by a link with the following qualification composition:

Section 1. ALARM SCHEMES

Table 1-146

Schemes for collecting and implementing information signals

Norm for 1 signal

Table 1-147

Schemes for the formation of a signaling section

Norm for 1 plot

Table 1-148

Mnemonic diagrams of the supervisory control panel

Norm for 1 scheme

Section 2. ELECTRICAL NETWORK INSULATION CONTROL SCHEMES

Table 1-149

Electric network insulation control schemes

Norm for 1 scheme

SECTION 11. MEASUREMENTS IN ELECTRICAL INSTALLATIONS

Introductory Instructions

1. This section provides the labor costs for testing and measuring in electrical installations and on electric cables in accordance with the requirements of the rules for the installation of electrical installations, SNiP 3.05.06-85 "Electrical devices", as well as the "Rules technical operation(PTE) of electrical installations of consumers” and “Safety regulations for electrical installations of consumers”.

2. This section contains the cost rates for work that was not included in the commissioning work of other departments of the collection, as well as for repeated measurements.

3. The rates, in addition to those listed in paragraph 6 of the technical part, take into account labor costs for the following commissioning:

choice of measurement method;

assembly and disassembly of test and measuring circuits;

ensuring safety measures at the test object (measurement);

measurement production.

4. In the norms from 1-152-2 to 1-152-5, 1-154-1, 1-156-1, labor costs for the installation of auxiliary electrodes and their connection with measuring instruments and measured objects.

5. Labor costs for measuring the insulation resistance of electrical machines, transformers, switching devices, relay protection and automation devices, voltage and operating current circuits, static converters, as well as devices for automatic control systems for electric drives are taken into account in the standards for setting up the above devices, devices and control systems for the relevant sections of this collection and additionally for this section 11 are not determined.

Labor costs for measuring the insulation resistance of control cables between consoles, panels, cabinets, control stations, as well as between individual devices are taken into account in the commissioning standards:

functional groups as part of automatic control and regulation systems - in department 9;

secondary switching circuits of power plants and substations - according to the relevant sections of this collection.

Additionally, according to this section, labor costs for these works are not determined.

6. Labor costs for measuring the insulation resistance of power wiring from starting device to the current collector are determined in the following order:

if the pantograph is an electric motor or a solenoid, then the labor costs are taken into account by the norm for commissioning for the specified equipment in department 7 and are not additionally determined in department 11;

if the current collector is a transformer or other electrical apparatus, taken into account by the nomenclature of this collection, then labor costs are taken into account by the norms of commissioning in department 2 and are not additionally determined in department 11;

if the current collector is an active resistance or other electrical apparatus not included in the nomenclature of this collection, then labor costs should be determined according to the norm 1-163-1 of this department;

for power wiring from the cabinet to the starting device (line), labor costs should also be determined according to the norm 1-163-1.

7. The standards of this section are calculated on the basis of the conditions for the implementation of commissioning by a link with the following qualification composition:

Section 1. CABLE WORK

Table 1-150

Search and determination of the location of cable damage with burning

Norms for 1 cable

Table 1-151

Determination of active resistance or working

electric capacitance of the cable core

Norms for 1 measurement

Section 2. GROUNDING DEVICES

Table 1-152

Current spreading resistance measurements

Norms for 1 measurement

Table 1-153

Checking the presence of a circuit between grounding conductors

and earthed elements

Norm per 100 points

Table 1-154

Determination of soil resistivity

Norm for 1 measurement

Home > Document

11 DEVICES AND ALARM CIRCUIT

11.1 Introductory notes

11.1.1 This section provides labor costs for commissioning for independent alarm circuits (central, technological, local, emergency, warning, etc.), including light and sound signals, as well as electric network insulation control circuits. 11.1.2 In norms other than those listed in clause 1.6 the technical part, the costs for the following commissioning works, carried out in accordance with the requirements of the Rules for Electrical Installations, as well as SNiP 3.05.06-85 "Electrical Devices", are taken into account: - checking and configuring relay-contactor and non-contact equipment; - setting the time relay settings; - adjustment of flashing light devices; - testing devices and signaling schemes for operation.

11.1.3. The norms do not take into account and should be determined additionally according to the norms of other sections of the Collection, the costs of commissioning for: - switching devices and their secondary switching circuits -according to the norms groups 15 to 19; - signaling circuit wiring diagrams - according to the norms of groups 41 to 42; - sensors, from which the signal enters the automatic control circuit, - according to the norms of groups 51 to 53; - tests with increased voltage - according to the standards of group 71. 11.1.4 The scope of work according to the norm 1-58-1 includes checking the signaling circuits from the first intermediate terminal block of signal-generating devices to the signaling section by creating modes or their artificial imitation (with in the absence of a site for the implementation of signals, it is carried out directly on a light or sound signal). 11.1.5 The scope of work in accordance with the norm 1-58-2 includes setting up the equipment of the signaling section and ensuring the functioning of light, sound and other signaling (including the RIS relay).

Group 58 Signaling schemes

Meter: signal (standard 1-58-1); plot (norm 1-58-2); scheme (standards 1-58-3 - 1-58-6, 1-59-1, 1-59-2). Group 58 (standards 1 to 6)

Resource name

unit of measurement

Scheme for collecting and implementing information signals of protection devices, automation of electrical and technological modes

The scheme for the formation of the signaling section (central, technological, local, emergency, warning, etc.)

Mnemonic diagram of the supervisory control panel with the number of received signals

for every 100 subsequent signals

Group 59 Electric network insulation monitoring schemes

Gauge: Schematic Group 59 (Norms 1 to 2)

Resource name

unit of measurement

Control scheme

using electrical measuring instruments

with the use of relay-contactor equipment and non-contact elements

Labor costs of commissioning personnel

12 MEASUREMENTS IN ELECTRICAL INSTALLATIONS

12.1 Introductory notes

12.1.1 This section provides labor costs for testing and measuring in electrical installations and on electrical cables in accordance with the requirements of the Rules for the Installation of Electrical Installations, SNiP 3.05.06-85 "Electrical Devices", as well as the "Rules of Technical operation (PTE) of electrical installations of consumers” and “Safety Rules for the operation of electrical installations of consumers” (1998, Kyiv). 12.1.2 This section lists the cost rates for work that was not included in the commissioning work of other sections of the Collection, as well as for repeated measurements. 12.1.3 In norms other than those listed in clause 1.6 works listed in clause 1.5 the technical part of the Collection takes into account labor costs for the following commissioning works: - selection of the measurement method; - assembly and disassembly of test and measurement circuits; - ensuring measures for labor protection at the object of testing (measurement); - production of measurements.

12.1.4 The rates from 1-61-1 to 1-61-5, 1-61-7, 1-61-9 take into account labor costs for the installation of auxiliary electrodes and their connection with measuring instruments and measured objects. 12.1.5 Labor costs for measuring the insulation resistance of electrical machines, transformers, switching devices, protection and automation devices, voltage and control current circuits, static converters, as well as devices for automatic control systems for electric drives are taken into account in the standards for setting up the apparatuses, devices and control systems listed above according to the relevant sections of this Collection and additionally according to this section are not determined.

Group 60 Cable work

Meter: cable (standards 1-60-1 - 1-60-3); measurement (standards 1-60-4, 1-60-5)

Group 60 (rates 1 to 5)

Resource name

unit of measurement

Search and determination of the location of damage to a cable with a live, cable length, m

Determination of active resistance or working electrical capacitance of a cable core at voltage, kV

for each subsequent 500 m

Group 61 Earthing devices

Meter: measurement (standards 1-61-1 - 1-61-5, 1-61-7); 100 points (norm 1-61-6); pantograph (standard 1-61-8); touch point (1-61-9)

Group 61 (rates 1 to 5)

Resource name

unit of measurement

Current flow resistance measurement

ground electrode

contour with a diagonal, m

Labor costs of commissioning personnel

End of group 61 (norms 6 to 9)

Resource name

unit of measurement

Checking the presence of a circuit between grounding conductors and grounded elements

Determination of soil resistivity

Measurement of the impedance of the "phase-zero" circuit

Characterization for determining the touch voltage at the points specified in the project

Labor costs of commissioning personnel

Group 62 Other measurements

Meter: measurement (standards 1-62-1 - 1-62-5, 1-62-7, 1-62-10, 1-62-11, 1-62-14, 1-62-16); characteristic (norm 1-62-6); phasing (norms 1-62-8, 1-62-9); oscillogram (standard 1-62-12); diagram (norm 1-62-13); line (norm 1-62-15); test (standards 1-62-17, 1-62-18). Group 62 (standards 1 to 5)

Resource name

unit of measurement

Measurement of the tangent of the dielectric loss angle

Measurement of DC transient resistance of busbar contacts of distribution devices with voltage, kV

Measurement of active, inductive resistance and capacitance of electrical machines and devices

Labor costs of commissioning personnel

Note. Norm 1-62-5 applies only to electrical machines and devices installed in power circuits.

Continuation of group 62 (norms 6 to 10)

Resource name

unit of measurement

Removal of temporary characteristics-teri-stick

Removal of speed characteristics of switching devices

Phasing of electric line or transformer with mains voltage, kV

Measurement of the absorption coefficient (P60 / P15) of the windings of transformers and electrical machines

Labor costs of commissioning personnel

Continuation of group 62 (norms 11 to 14)

Resource name

unit of measurement

Measuring the coefficient of non-linearity of the insulation of an electrical machine

Removal, processing and analysis of oscillograms

Removal and analysis of vector diagrams

Measurement of leakage currents or breakdown voltage of an arrester or leakage currents of a voltage limiter

Labor costs of commissioning personnel

End of group 62 (norm from 15 to 18)

Resource name

unit of measurement

Measurement of insulation resistance with a megohmmeter

Free flow test of transformer oil and measurement of the impregnation coefficient of the cable line low pressure(hydraulic and impregnation tests)

Breakdown oil test

cable and other lines with voltage up to 1 kV, intended for the transmission of electricity to switchgear, switchboards, cabinets and switching devices

winding machines, apparatus and wires

Labor costs of commissioning personnel 1.1 This Collection contains resource elemental estimated norms for commissioning (RESNpn), necessary to determine the need for labor costs when performing commissioning for refrigeration, compressor and carbon dioxide

  • Rules for determining the cost of construction dbn d 1-1-2000, as amended in accordance with Addendum No. 3, approved by order (1)

    Document

    2.12 ADDITIONAL REQUIREMENTS FOR THE DEVELOPMENT OF ESTIMATE DOCUMENTATION FOR EXPANSION, RECONSTRUCTION AND TECHNICAL RE-EQUIPMENT OF ENTERPRISES, BUILDINGS AND FACILITIES 30

  • 1. This section provides the labor costs for commissioning for independent signaling circuits (central, technological, local, emergency, warning, etc.), including light and sound signals, as well as electric network insulation monitoring circuits.

    2. The rates, in addition to those listed in clause 6 of the technical part, take into account the costs of the following commissioning work performed in accordance with the requirements of the rules for electrical installations, as well as SNiP 3.05.06-85 "Electrical devices":

    testing and adjustment of relay-contactor equipment;

    setting the time relay settings;

    adjustment of flashing light devices;

    testing devices and signaling schemes for operation.

    3. The norms do not take into account and should be determined additionally according to the norms of other departments of the collection, the costs of commissioning for:

    switching devices and their secondary switching circuits - in department 3;

    wiring diagrams for signaling circuits - for department 6;

    sensors, from which the signal enters the automatic control circuit - according to department 9;

    high voltage tests - according to department 12.

    4. In the composition of works according to the table. 1-146 includes checking the signaling circuits from the first intermediate terminal block of the devices that form the signal to the signaling section by creating a mode or their artificial imitation (in the absence of a signal implementation section, it is carried out directly to a light or sound signal).

    5. In the composition of works according to the table. 1-147 includes setting up the alarm section equipment and ensuring the operation of light, sound and other alarms (including the RIS relay).

    6. The norms of this section are calculated based on the conditions for the implementation of commissioning by a link with the following qualification composition:

    Section 1. ALARM SCHEMES

    Table 1-146

    Schemes for collecting and implementing information signals

    Norm for 1 signal

    Table 1-147

    Schemes for the formation of a signaling section

    Norm for 1 plot

    Table 1-148

    Mnemonic diagrams of the supervisory control panel

    Norm for 1 scheme


    Mnemonic diagram with the number of received signals

    Cost elements (resources)

    Unit

    before

    for every 100

    measurements

    50

    100

    200

    subsequent signals

    1-148-1

    1-148-2

    1-148-3

    1-148-4

    Labor costs of commissioning personnel

    man-hour

    171

    232

    389

    168